Safe
Erecting and Dismantling Procedures
Erection
Procedure
The
foundation for system scaffolds should be prepared in the same way as
other types of scaffolding, ensuring a firm level base, and using
mudsills, base plates, and adjustable screw jacks. The base plates
should be laid out in what you estimate is the correct location (LOOK
UP). We recommend starter collars since they allow scaffolds to be
laid out level and square. The first level of transoms and ledgers
should be placed on the starter collars and be leveled using the
screw jacks. When the scaffold is square and level you should tighten
the connections and nail the base plates to the mudsills. At this
point set up an erection platform for installing the standards for
the next lift. You now install the second level ledgers and transoms
as well as the deck. You must install ledger bracing at the ends of
all system scaffolds and at intervals according to the manufacturers’
recommendations. Each brace will be the correct length for the span
being braced and should be connected to the attachment point on the
standard. You must install face or sway bracing according to
Manufacturer instructions. Again, attachment points are set on the
standards, and the braces come in specific lengths for the span of
the scaffold being constructed. Normally, every third bay is braced
for sway.
Guardrails
Generally,
guardrails are installed at all
working
levels. They attach directly to the connection points on the
standards.
TRAINING
Workers
must be properly trained or instructed before they use equipment.
Only competent workers may construct scaffolds.
INSPECTION
Inspect
all equipment before using. Never use any equipment that is damaged
or defective in any way.
SITE
EVALUATION
When
possible, always survey the job site to identify any potential hazard
condition. Complete jobsite hazard evaluation and amend your
standard fall protection plan with site-specific requirements.
FOUNDATIONS
Never
construct a scaffold on unprepared foundations. Where necessary,
provide adequate continuous wood sills and ensure that they are not
less than 50mm x 250mm (2” x 10”) and cover two frame legs in
length. Footings, sills, or supports must be capable of supporting
at least 2 times the maximum load to which they are subjected without
settlement. Any part of a building or structure that is used to
support the scaffold shall be capable of supporting the maximum
intended load to be applied, and must be verified by a professional
engineer.
BASE
Always
use adjustable bases with system scaffolds and other components that
the manufacturer recommends. Level the base by starting at the
highest point of ground level and ensure accuracy, so you do not have
to level the scaffold after the base has been completed.
STANDARDS
Standards
are manufactured in pre-determined lengths and the spacing of
standards is dependent upon the loading to be imposed on the
scaffold. Always check loading requirements and if necessary, seek
approved engineered drawings.
LEDGERS
Connect
the ledgers to the standard at the desired lift height by positive
connection. Ledgers are manufactured in pre-determined lengths and
the bay size is normally determined by loading criteria. The
vertical spacing or lift height between ledgers should not exceed
1.98m (6’-6”). Any ledger that is longer than 1.52m (5’-0”)
and is supporting a load should be a double ledger or equivalent.
BRACING
– Internal (a)
As
bracing has a pre-determined length, select the correct size of
bracing, and brace standards internally every 6m (20’-0”) in
length, and ensure that bracing extends to the full height of the
scaffold.
BRACING
– Sway (b)
Sway or
façade bracing should be installed on the outside face of the
scaffold to full height, and can be either in one single bay or
extended across multiple bays. If single-bay bracing is selected, it
must be in both end bays and at least every 15m (50’-0”)
longitudinally. In the multiple-bay configuration, the desired angle
is 45 degrees to the horizontal, close to the note point, and this
should be continuous to full height, and in many cases will be
designed by an engineer.
BRACING
– Plan (c)
Plan
bracing (horizontal diagonal) is recommended and often required. As
a minimum, it should be installed at the base and on the same level
as the scaffold ties.
SCAFFOLD
TIES
Where the
scaffold height exceeds three times the smallest base dimension (3:1
ratio), scaffolds must be tied at least every 4.57m (15’-0”)
interval vertically and 6m (20’-0”) horizontally. Where
possible, push/pull ties should be used, ensuring that the tie tube
is connected to both standards (or to both ledgers near the standard)
with right angle clamps. Tie tubes should be installed on the same
bay as the internal bracing. If it is not possible to tie the
scaffold to a structure, a professional engineer must provide special
design considerations.
WORK
PLATFORMS
The work
platform provides the worker with a safe environment from which to
work. The work platform must consist of a fully-planked/-decked
surface and shall have guardrails consisting of top rails, mid rails,
and toe boards installed on all open sides. Toe boards shall be
installed at the edge of all work platforms and shall be a minimum
100mm (4”) high.
GUARDRAILS,
MIDRAILS
Guardrails
must be installed on all open sides of the scaffold where a person
can fall a distance of 2.4m (8’-0”) or more, and shall be not
less than 0.92m (3’) nor more than 1.07m (3’-6”) above the
platform, and should be positively connected to the standards. Mid
rails should be installed equidistant between the guardrail and the
platform.
PLANKS
– WOOD
Always
use select structural wood plank, LVL (laminated veneer lumber), or
equivalent approved 50mm x 250mm (2”x10”) lumber, of uniform
thickness. Ensure that wood plank extends a minimum 150mm (6”) and
no more than 300mm (12”) beyond the centre of supports and has
cleats at one end to prevent lateral movement. Wood planks should
not span a length greater than 2.13m (7’-0”) unless engineered
otherwise.
PLANKS
– STEEL
Most
steel planks have a supporting hook and wind lock to prevent uplift.
Ensure that the steel plank has a non-skid surface and that the load
capacity rated by the manufacturer is not exceeded. Always ensure
that the wind lock is in the closed position.
MANUFACTURED
DECKING
These are
normally constructed from aluminum side frames with a plywood or
metal decking and are secured to the scaffold by supporting hooks
with wind locks that prevent uplift. The load capacity is identified
on the deck and must not be exceeded. Always ensure that the wind
lock is in the closed position.
LADDERS
Ladders
are used to gain access to the working platforms. Ladders, ladder
cages, and rest platforms, when installed on scaffolds, must conform
to all applicable codes, and must extend approximately 1m (3’-0”)
above the landing area and be secured. Always maintain 3-point
contact at all times when climbing.
STAIRWAYS
Manufactured
modular stairways are used to gain access to working platforms and
must be installed in accordance with the manufacturer’s
instructions.
SIDEBRACKETS
Side
brackets must be installed at right angles to the scaffold and should
be installed in accordance with manufacturer’s instructions. They
are an extension of the work platform and must accommodate at least 2
planks and must not be used for storage of materials. Always check
maximum loading of side brackets.
CANTILEVERS
Cantilever
platforms, except fabricated side brackets, must be designed by a
professional engineer and shall be installed in accordance with
supplier’s/manufacturer’s instructions.
LOADING
The load
on a scaffold must never exceed the safe working load that it was
designed for. Most scaffolds are required to support at least four
times the intended load, however this varies in different
jurisdictions and must be checked. When any unusual load conditions
apply, or when the load exceeds 3.5 kN/m (75psf), the scaffold must
be designed by a professional engineer.
ENCLOSURES
If the
scaffold has tarpaulins or any enclosure system attached, this
imposes additional wind loading and must be designed accordingly.
Double-wrap #9 wire ties will have a safe working load range from
600lb-800lb with a safety factor of 4:1, keeping that in mind
Scaffolds should have ties at every leg every level and be
constructed of a tube and clamp system or #9 double wire.
POWER
LINES
It is
dangerous to construct a scaffold close to power lines. Always
consult the power company for specific guidelines and conform to all
applicable codes.
FALL
ARREST
In
certain jurisdictions, unless a safety net or travel restraint system
is being used, workers shall wear fall arrest systems if the workers
may fall a distance of more than 3m (10’-0”).
Dismantling
Dismantling
system scaffolds is essentially erection in reverse. Each tier should
be completely dismantled and the material lowered to the ground
before beginning to dismantle the next tier. If platform sections or
planks have been left at each level during erection, as suggested
above, it should be relatively easy to lower platform materials from
above and deck in the current working platform completely. Extra
platform material can be lowered to the ground. Using this procedure,
workers will be operating most of the time from a fully decked-in
platform. This makes for easier removal of braces and frames.
Dismantled materials should be lowered using a gin wheel and hoist
arm or by mechanical means. Dropping materials not only causes damage
and waste, but also endangers workers below—and is illegal. When
scaffolds have been in the same location for a long time, pins and
other components frequently rust, braces become bent, and materials
such as mortar or paint often build up on the scaffold parts. All of
these can prevent components from separating easily. Removing jammed
or rusted scaffold components can be very hazardous. Tugging or
pulling on stuck components can cause you to lose your balance and
fall.
Workers
should wear a full body harness and lanyard tied off to a scaffold
frame or lifeline before attempting to loosen stuck or jammed parts.
Dismantling
tube-and-clamp and systems scaffolding must proceed in reverse order
to erection. Each tier should be completely dismantled as far as
connections will allow before you begin dismantling the lower tier.
You must dismantle them this way because the bracing for tube-and
clamp scaffold is not located in each bay as it is for frame
scaffolding. The span or spans with front sway bracing should be the
last to be dismantled on each tier.
Please
refer to the Construction health and safety manual for a more
detailed reference.
All
scaffolds shall exceed or at least comply with OHSA Acts and
Regulations
No comments:
Post a Comment